A luxury kitchen remodel in Los Angeles in 2026 typically runs $150,000 to $500,000, takes 14 to 22 weeks on the construction side, and turns on three structural decisions made in the first month — whether a wall comes down, whether the island moves, and whether cabinetry is custom or semi-custom. Cabinetry plus appliances absorb roughly 60% of total cost on a high-end build. We Do Construction — a Los Angeles design-build firm licensed in California (CSLB #1096552) and listed in the Architectural Digest PRO Directory — has delivered these projects across Beverly Hills, Brentwood, Pacific Palisades, and Santa Monica. The Camden Drive Kitchen, a recent 480-square-foot full gut in Beverly Hills, is a working illustration of how those early structural decisions drive everything that follows — cost, schedule, and what the room actually feels like at completion.

Project

Camden Drive Kitchen

Neighborhood

Beverly Hills · 90210

Scope

Full gut · wall removal · structural beam

Square Footage

480 sf · island-and-perimeter

Cabinetry

Custom rift white oak · panel-front appliances

Delivery

Design-build · WDC

$150–500KTotal Investment
Luxury LA
14–22Weeks
Construction
60%Cabinetry +
Appliances
4–8Weeks
Design + Permit
I · The Numbers

The numbers most homeowners need to hear first

Beverly Hills kitchen island — custom cabinetry, panel-front appliances
Beverly Hills kitchen island — rift white oak cabinetry, integrated panel-front appliances, single slab counter.

Three pricing tiers cover most of the LA luxury-kitchen market:

$150–225KRefresh tier. Existing footprint, semi-custom cabinetry, mid-tier panel-front appliances, single counter material.
$225–350KReconfigure tier. Wall removed, island repositioned, custom cabinetry, integrated Sub-Zero/Wolf, two counter materials.
$350–500KArchitectural tier. Structural changes, custom millwork, La Cornue / Lacanche range, hand-glazed tile, integrated pantry, butler’s prep.
$500K+Volume + addition. When the kitchen reframes the floor plan or pushes into new square footage, the project becomes a full-home scope.
II · The Drivers

What actually drives cost in a Los Angeles kitchen

Five line items absorb the majority of every luxury LA kitchen budget. Knowing the proportions early is the difference between a project that lands on number and one that drifts:

  • Cabinetry: 28–38% of total. Custom rift oak or fumed walnut from a local mill, mortise-and-tenon, soft-close everywhere, integrated lighting.
  • Appliances: 18–25%. Sub-Zero refrigeration column + freezer column, Wolf range or Lacanche, Miele dishwasher (often two), Best or Vent-A-Hood liner.
  • Counters + backsplash: 8–14%. Single-slab quartzite or honed marble, full-height splash, water-jet detail at the range wall.
  • Structural + electrical + plumbing: 12–18%. Beam where the wall came down, sub-panel upgrade, gas line resize, hood ductwork through second story.
  • Tile, flooring, paint, lighting, fixtures, labor margin: the remainder.

Sixty percent of the budget is the millwork shop and the appliance package. The rest is structure, finish, and how well the field crew can hold tolerance on the cabinet install.— Jacob Bachar, WDC

III · The Structure

Permits, walls, and structural decisions

Three structural questions answer themselves in the first design meeting:

  1. Does a wall come down? If yes, the project crosses into LADBS structural permit territory — engineered beam, lateral analysis, post-installed connection details. Add 4–6 weeks to the calendar and $25,000–$60,000 to the budget.
  2. Does the island move? Island repositioning typically requires re-routing gas, water, drain, electrical, and dedicated circuits through the slab or crawl space. Cost: $8,000–$22,000 depending on the slab condition.
  3. Does the hood vent to the roof? Code-compliant make-up air for a 1,200+ CFM hood requires a dedicated path. Two-story homes with a kitchen below routinely need ductwork through closets or pilasters.

A WDC pre-design walk-through identifies these three decisions in the first hour. Skipping the walk-through is the most common reason kitchen remodels go over schedule.

IV · The Cabinetry

The cabinetry decision

Beverly Hills kitchen detail — custom rift white oak
Cabinetry detail — rift-sawn white oak, finger-pull edge, integrated touch-latch.
Brentwood kitchen — full custom millwork
Brentwood kitchen — full custom millwork, single-slab honed marble counter.

Custom millwork from a Southern California shop is the through-line on every WDC luxury kitchen. The semi-custom path (RTA-shop boxes with custom doors) saves 25–40% on the cabinetry line but visibly fails on three details: drawer-front alignment around appliances, panel matching at the refrigerator, and crown-and-base transitions at uneven walls. On a kitchen at this budget, the savings rarely justify the visual cost. Where semi-custom does work: utility rooms, butler’s pantries, deep storage where appliance integration is not on the line.

The line between a $200K kitchen and a $350K kitchen runs through the cabinet shop. Custom millwork buys tolerance — the room finishes flush, even, and integrated. Semi-custom shows its compromises at the appliance line.— On cabinetry tiers

V · Schedule

Timeline, end to end

  • Design + selections: 4–6 weeks
  • Permitting (if structural): 4–8 weeks, runs in parallel with cabinet ordering
  • Cabinetry lead time: 10–16 weeks from order to delivery
  • Demo + rough trades: 2–3 weeks
  • Cabinet install + finish trades: 8–12 weeks
  • Punch + appliance commissioning: 1–2 weeks
  • Total construction: 14 to 22 weeks. Total from kickoff to dinner: 22 to 32 weeks.

What the numbers actually look like

$150–500KTotal investment. 2026 luxury LA kitchen, design-build delivery.
22–32 wksKickoff to dinner. Design through punch list.
60%Cabinetry + appliances. Combined share of total budget.
$25–60KWall removal delta. Beam, engineering, permit, structural work.
Pre-Construction Walk-Through

Considering a luxury kitchen remodel?

A two-hour pre-construction walk-through identifies the three structural questions (wall, island, hood), establishes the budget tier, and produces a realistic 22–32 week schedule. The earliest a builder should be in the conversation is before cabinetry selections begin.

Schedule a Walk-Through

VI · Delivery

Why design-build on a kitchen remodel

Architect-led-then-bid sequences expose kitchen-remodel owners to two recurring problems: the cabinet shop receives drawings that do not account for actual field conditions (out-of-plumb walls, soffits, mechanical chases), and the general contractor inherits a finish schedule priced against last year’s appliance market. Design-build collapses both gaps. The cabinet shop walks the room with the field crew before drawings finalize. The appliance and tile selections lock at the price the build is contracted at.

Design-build remodeling works particularly well on kitchens because the system is bounded: a single room, a fixed set of trades, a known appliance ecosystem. The variance lives entirely in the millwork and the finish layer — and those are exactly the variables a design-build team controls best.

FAQ

Frequently asked questions

How much does a luxury kitchen remodel cost in Los Angeles?
$150,000 to $500,000 in 2026 for the luxury tier. Refresh tier (existing footprint, semi-custom) lands $150–225K. Reconfigure (wall down, custom millwork, integrated appliances) lands $225–350K. Architectural tier (structural, full custom, La Cornue range, butler’s prep) lands $350–500K.
How long does a kitchen remodel take?
14 to 22 weeks of construction. Including design and permitting, kickoff to dinner runs 22 to 32 weeks total. Cabinetry lead time (10–16 weeks) is the longest single line item.
Do I need permits for a kitchen remodel in LA?
Yes if any wall comes down, the island moves significantly, the panel needs upgrading, or the hood vent path changes. Cosmetic refreshes (cabinets in place, no electrical or plumbing changes) can sometimes proceed without permit, but most luxury-tier projects involve at least one permitted change.
What drives kitchen remodel cost the most?
Cabinetry plus appliances absorb roughly 60% of total cost. Structural changes (wall removal, beam) add $25K–$60K. Counter material (quartzite vs marble vs porcelain), backsplash detail, and tile selection drive the remaining variance.
When should a wall come down in a kitchen remodel?
When the existing kitchen is closed off from a primary living space and the program calls for an island that doubles as a gathering spot. Wall removal adds 4–6 weeks and $25K–$60K, but typically delivers the largest perceived improvement in the room.
JB

Jacob Bachar

Founding Builder, We Do Construction

Jacob leads design-build construction and remodeling for We Do Construction across Los Angeles. WDC is licensed in California (CSLB #1096552) and listed in the Architectural Digest PRO Directory. Los Angeles office: (818) 590-5206, Monday–Friday 8–5.

Licensed in California  ·  CSLB #1096552  ·  AD PRO Directory 2025 + 2026  ·  (818) 590-5206  ·  Mon–Fri 8–5

ENGAGEMENT · BY APPLICATION REVIEWED BY THE PRINCIPAL · WITHIN 48 HOURS

A NOTE BEFORE APPLYING

Apply for
Discovery.

WDC engages a limited number of full-home projects per year. Applications are reviewed personally by the principal — not by an intake coordinator, not routed to a sales pipeline. Discovery is a 90-minute conversation, fixed fee, with a written feasibility memo whether or not we proceed together.

01

Submit the application below. Real address, real budget envelope.

02

If the project is a fit, the principal responds within 48 hours.

03

Discovery scheduled at the WDC office or your residence. Fixed fee.

04

Feasibility memo delivered within seven days. Engagement decision yours.

APPLICATION

01

Who you are

02

The project

03

Anything we should know